Revamp project of berth no. 2 & 3 of Suanshan wharf of ZRCC passed final acceptance
Revamp project of berth no. 2 & 3 of Suanshan wharf of ZRCC passed final acceptance
-
On January 12, the revamp project of berth no. 2 & 3 of Suanshan wharf of ZRCC harbour affairs and storage department passed final acceptance, which is organized by Ministry of Transport of PRC.
-
Xiao Daxuan,deputy director of Water Transport Bureau of Ministry of Transport of PRC, LI Li,deputy general manager of ZRCC and experts from Ministry of Transport, provincial and municipal transport departments, Municipal Development and Reform Commission, Bureau of Municipal Marine affairs, Municipal Ocean Bureau, Environmental Protection Bureau, Safety Supervision Bureau and Fire Administration, attended the project acceptance meeting.