First main plant of ZRCC ethylene project achieved mechanical completion

First main plant of ZRCC ethylene project achieved mechanical completion

--

On November 26th afternoon, MTBE/Butylene-1 plant, one of ten main plants of ZRCC ethylene project with annual production of 110 KTA MTBE and 40 KTA butylene-1, firstly achieved the mechanical completion, which marked the prelude to the mechanical completions of main ethylene plants.

--

With the proprietary technology of SINOPEC Technology Development Company (ST), MTBE/Butylene-1 plant produces MTBE and butylene-1 from C4 raffinate and industrial methanol, which are produced by the Butadiene Extraction Plant. For MTBE/Butylene-1 plant, its civil work was started on July 14th, 2008; civil foundation was completed on December 29th, 2008; main part of this plant was construction completed on October 2009, the Work lasted 500 days.

--

On November 26th morning, the Ethylene Project Management Department arranged the related departments (i.e. production, instrument, electrical departments, etc.) to implement specialty acceptance check, confirming the MTBE/Butylene-1 plant has reached the standard of mechanical completion.

Information source: 
2009-12-02